Rothesay Pier Settlement - Phase 2 (Grouting & Piling Works) - Re-tender
Settlement has occurred behind the existing quay wall, specifically to the backfill of the old masonry pier over an approx. length of 120m at Rothesay Pier. The 1st phase of work, completed last year, consisted of the installation of a 5.6m high scour screen along the length to reduce thrust and wave action against the wall and protect and prevent further deterioration of the masonry wall. This contract (Phase 2) aims to address the settlement and prevent sliding failure of the wall by construction of a relieving R...
Buyer
Argyll and Bute Council
Value
Not provided
Published
31 Aug 2021
Closes
31 Aug 2021
Procurement details
Source
Pcs
Region
Scotland
Procurement method
Not provided
Category
Works
Contract starts
Not provided
Contract ends
Not provided
CPV classifications
45262340
Grouting work
44212400
Piling
Lots
Lot 1 Rothesay Pier Settlement - Phase 2 (Grouting & Piling Works) - Re-tender
Value not provided
Settlement has occurred behind the existing quay wall, specifically to the backfill of the old masonry pier over an approx. length of 120m at Rothesay Pier. The 1st phase of work, completed last year, consisted of the installation of a 5.6m high scour screen along the length to reduce thrust and wave action against the wall and protect and prevent further de...
Delivery: Lochaber, Skye & Lochalsh, Arran & Cumbrae and Argyll & Bute
Documents
Unlock document linkRothesay Pier Settlement - Phase 2 (Grouting & Piling Works) - Re-tender
Not provided
Settlement has occurred behind the existing quay wall, specifically to the backfill of the old masonry pier over an approx. length of 120m at Rothesay Pier. The 1st phase of work, completed last year, consisted of the installation of a 5.6m...
Planned procurement notice · Web page