Pipeline Noticeocds-r6ebe6-0000630230

Rothesay Pier Settlement – Phase 2 (Grouting & Piling Works)

Settlement has occurred behind the existing quay wall, specifically to the backfill of the old masonry pier over an approx. length of 120m at Rothesay Pier. The 1st phase of work, completed last year, consisted of the installation of a 5.6m high scour screen along the length to reduce thrust and wave action against the wall and protect and prevent further deterioration of the masonry wall. This contract (Phase 2) aims to address the settlement and prevent sliding failure of the wall by construction of a relieving R...

Buyer

Argyll and Bute Council

Value

Not provided

Published

9 Sept 2020

Closes

9 Sept 2020

Procurement details

Source

Pcs

Region

Scotland

Procurement method

Not provided

Category

Works

Contract starts

Not provided

Contract ends

Not provided

CPV classifications

45262340

Grouting work

Lots

Lot 1 Rothesay Pier Settlement – Phase 2 (Grouting & Piling Works)

Value not provided

Settlement has occurred behind the existing quay wall, specifically to the backfill of the old masonry pier over an approx. length of 120m at Rothesay Pier. The 1st phase of work, completed last year, consisted of the installation of a 5.6m high scour screen along the length to reduce thrust and wave action against the wall and protect and prevent further de...

Delivery: Lochaber, Skye & Lochalsh, Arran & Cumbrae and Argyll & Bute

Rothesay Pier Settlement – Phase 2 (Grouting & Piling Works)

Not provided

Settlement has occurred behind the existing quay wall, specifically to the backfill of the old masonry pier over an approx. length of 120m at Rothesay Pier. The 1st phase of work, completed last year, consisted of the installation of a 5.6m...

Planned procurement notice · Web page