A91 Guardbridge Cathodic Protection and Concrete Repairs
New Bridge at Guardbridge shows areas of spalled concrete and exposed corroding reinforcement. Concrete repairs are required and an impressed current cathodic protection (CP) system shall be installed to mitigate further deterioration of the bridge.
Buyer
Fife Council
Value
£1,250,000
Published
12 Mar 2019
Closes
8 Apr 2019
Procurement details
Source
Pcs
Region
UKM72
Procurement method
Open
Category
Works
Contract starts
Not provided
Contract ends
Not provided
CPV classifications
45221100
Construction work for bridges
45223000
Structures construction work
Lots
Lot 1 A91 Guardbridge Cathodic Protection and Concrete Repairs
£1,250,000
This is an Open Procurement. Assessment will be undertaken in two stages. Stage 1 is the Tender assessment - 'Award Criteria.' The Contractor with the Most Economically Advantageous Tender will be afforded the work. Stage 2 is the ESPD 'Selection Criteria'. Economic operators may be excluded from this competition if they do not meet the minimum requirements...
Delivery: UKM72
Documents
Unlock document linkA91 Guardbridge Cathodic Protection and Concrete Repairs
Not provided
New Bridge at Guardbridge shows areas of spalled concrete and exposed corroding reinforcement. Concrete repairs are required and an impressed current cathodic protection (CP) system shall be installed to mitigate further deterioration of th...
Contract notice · Web page
Guardbridge Information to Tender_for info only
12 Mar 2019
Guardbridge Contract Data_COMPLETE
12 Mar 2019
Word document
Guardbridge Tenderers Submission_COMPLETE
12 Mar 2019
Word document
Guardbridge Insurance Certificate_COMPLETE
12 Mar 2019
Word document
Guardbridge Bill of Quantities_COMPLETE
12 Mar 2019
Excel spreadsheet
Guardbridge Vol 3 Works Information_for info only
12 Mar 2019
ZIP archive
Guardbridge Vol 4 Site Information_for info only
12 Mar 2019
ZIP archive
MMD-349042-0001 Rev P3 supersedes MMD-349042-0001 Rev P2.
26 Mar 2019
X13 Performance Bond - revised
26 Mar 2019
Word document
10m buffer zones around Holts 1 and 2, and Couch 1 and 2. Indicative only, see TQ further info.
26 Mar 2019
Answer to TQ submitted 22.03.2019
26 Mar 2019
Contains public sector information licensed under the Open Government Licence v3.0.