Awarded Contractocds-h6vhtk-04ec42

LT107/108 Strathy Wood & LT229/230 Strathy South Grid Transformer

The Strathy Wood Windfarm Connection project proposes the establishment of a 132/33kV substation to allow the connection of the Strathy Wood windfarm on the network. The proposed substation is to have a single 132/33kV 90 MVA transformer (GT1) bay established at the windfarm with associated switchgears. The Strathy South project proposes the establishment of a 132/33kV substation to allow the connection of the Strathy South windfarm on the network. The proposed substation is to have a two 132/33kV 120 MVA transform...

Buyer

SSE plc

Value

Not provided

Published

12 Mar 2025

Closes

12 Mar 2025

Procurement details

Source

Find a Tender

Region

Highlands and Islands

Procurement method

Selective

Category

Works

Contract starts

Not provided

Contract ends

Not provided

CPV classifications

45231400

Construction work for electricity power lines

65310000

Electricity distribution

Lots

Lot 1 LT107/108 Strathy Wood & LT229/230 Strathy South Grid Transformer

Value not provided

The Strathy Wood Windfarm Connection project proposes the establishment of a 132/33kV substation to allow the connection of the Strathy Wood windfarm on the network. The proposed substation is to have a single 132/33kV 90 MVA transformer (GT1) bay established at the windfarm with associated switchgears. The Strathy South project proposes the establishment of...

Delivery: Caithness & Sutherland and Ross & Cromarty

Documents

No document metadata is available for this public record.

Contains public sector information licensed under the Open Government Licence v3.0.