Pipeline Noticeocds-h6vhtk-03f69b

PRO004738-Works-Contract- MBC Biomethane and CO2 Plant

UU (United Utilities Water Limited) UU are proposing to install new Gas to Grid upgrading plant with a Biomethane / CO2 carbon capture (liquified) that takes all the on-site generated gas (~ 6000nm3/hr) from our existing Anaerobic digestion storage for export into the gas network. Developing our future strategy we are undertaking pre-market research to understand market offerings for the following services UU are interested in understanding how this model can be delivered, and the best technical solution Responses...

Buyer

United Utilities Water Limited

Value

£30,000,000

Published

24 Aug 2023

Closes

24 Aug 2023

Procurement details

Source

Find a Tender

Region

North West (England)

Procurement method

Not provided

Category

Works

Contract starts

Not provided

Contract ends

Not provided

CPV classifications

45251240

Landfill-gas electricity generating plant construction work

45222110

Waste disposal site construction work

45251141

Geothermal power station construction work

45251220

Cogeneration plant construction work

45252122

Sewage digesters

45255800

Gas-production plant construction work

Lots

Lot 1 PRO004738-Works-Contract- MBC Biomethane and CO2 Plant

Value not provided

UU (United Utilities Water Limited) UU are proposing to install new Gas to Grid upgrading plant with a Biomethane / CO2 carbon capture (liquified) that takes all the on-site generated gas (~ 6000nm3/hr) from our existing Anaerobic digestion storage for export into the gas network. UU are interested in understanding how this model can be delivered, and the be...

Delivery: North West (England)

Documents

No document metadata is available for this public record.

Contains public sector information licensed under the Open Government Licence v3.0.