Conveyor Overhauls, Repairs and Maintenance
Lot 1 - Conveyor Shaft Overhauls - Labour and Materials Lot 2 - Conveyor Repairs and Maintenance - Labour and Materials Lot 3 - Conveyor Ladder kits - Materials
Buyer
Network Rail Infrastructure Ltd
Value
£4,808,440
Published
29 Nov 2021
Closes
11 May 2021
Procurement details
Source
Find a Tender
Region
United Kingdom
Procurement method
Selective
Category
Goods
Contract starts
Not provided
Contract ends
Not provided
CPV classifications
42417200
Conveyors
42417300
Conveyor equipment
42419800
Parts of conveyors
42417310
Conveyor belts
71311230
Railway engineering services
Lots
Lot 1 Conveyor Shaft Overhauls
£701,440
The supplier is required to overhaul idler and drive conveyor shafts to OEM standard during all modular maintenance works on all conveyors on the following vehicle types (RM900, SPW, NBPW, VM80, 09CM, MFS-D, MFS-SB). The shafts can be overhauled offsite but will be collected and delivered to Holgate. The volume is dependent on the number of MFS Main Conveyor...
Delivery: United Kingdom
Lot 2 Conveyor Repairs and Maintenance
£1,122,000
To carry out ad hoc conveyor repairs and servicing. These conveyor repairs and servicing are above the current scope of basic maintenance activities that are undertaken by the High Output team, where a supplier can provide expert knowledge and assistance. The requirements include the provision of modifications to various parts within the conveyor assembly. T...
Delivery: United Kingdom
Lot 3 Conveyor Ladder Kits
£1,030,000
These are required to support the BCS overhaul programme in the future (type a) and Main Conveyor Overhauls (type b), Type b conveyor chain and support kits and may be purchased directly by Network Rail or by the outsourced supplier outside of this agreement, to support any outsourced overhaul strategy. Type B volume is dependent on the number of MFS Main Co...
Delivery: United Kingdom
Lot 4 Main Conveyor Overhauls (Parts or Labour and Parts)
£1,955,000
Single Tender Action with the manufacturer. The Supplier is required either to supply parts only to support in house overhauls or labour and materials to overhaul the bottom conveyor on up to 44 x MFS Wagons in batches of 5 at the supplier’s preferred location. The overhaul is part of the Year 2 of CP6 planned overhaul work, although will be carried out if r...
Delivery: United Kingdom