Open Tenderocds-b5fd17-f71085e9-046f-4543-a020-ddf688edcc34

RoW Mead Lane

This specification/pre-construction information is for the design, supply and installation of a new footbridge over the River Brue in West Lydford, Mendip. The footbridge links public footpath SM 14/22 to public bridleway SM 14/12 in the Parish of Lydford-on-Fosse. The footpath forms part of a wider network of very popular paths. The old bridge was collapsing and has been demolished and removed from site. Bank stabilisation has been been installed in the form of rock roll toe on top of the bottom courses of the old...

Buyer

SOMERSET COUNCIL

Value

£60,000

Published

8 Jan 2020

Closes

24 Jan 2020

Procurement details

Source

Contracts Finder

Region

Somerset

Procurement method

Open

Category

Works

Contract starts

Not provided

Contract ends

Not provided

CPV classifications

45221113

Footbridge construction work

Lots

Lot default RoW Mead Lane

£60,000

This specification/pre-construction information is for the design, supply and installation of a new footbridge over the River Brue in West Lydford, Mendip. The footbridge links public footpath SM 14/22 to public bridleway SM 14/12 in the Parish of Lydford-on-Fosse. The footpath forms part of a wider network of very popular paths. The old bridge was collapsin...

Delivery: South West · United Kingdom, South West, United Kingdom

Opportunity notice on Contracts Finder

8 Jan 2020

Opportunity notice on Contracts Finder

Tender notice · Web page

Contains public sector information licensed under the Open Government Licence v3.0.