YNE - AOMR Lot 1 NE Bywell Bank Stabilisation
To undertake a ground investigation and the subsequent analysis to determine the cause of the bank slippage that occurred at Bywell gauging station following Storm Desmond in 2015, together with the risk / likelihood of future slippage / movements at the site and the associated impacts on the existing infrastructure and its usage. Develop solutions to address these risks; short term and long term as necessary with the aim of agreeing a preferred option(s).
Buyer
Environment Agency
Value
£87,700
Published
4 Jun 2025
Closes
3 Jun 2025
Procurement details
Source
Contracts Finder
Region
United Kingdom
Procurement method
Selective
Category
Works
Contract starts
3 Jun 2025
Contract ends
31 Oct 2025
CPV classifications
45246000
River regulation and flood control works
Lots
Lot default YNE - AOMR Lot 1 NE Bywell Bank Stabilisation
£87,700
To undertake a ground investigation and the subsequent analysis to determine the cause of the bank slippage that occurred at Bywell gauging station following Storm Desmond in 2015, together with the risk / likelihood of future slippage / movements at the site and the associated impacts on the existing infrastructure and its usage. Develop solutions to addres...
Delivery: North East · United Kingdom, North East, United Kingdom
Documents
Unlock document linkAwarded contract notice on Contracts Finder
4 Jun 2025
Awarded contract notice on Contracts Finder
Award notice · Web page
Lot 1 - Civil Engineering NEC4 ECSC V1.1 (1)_Bywell Signed_Redacted
Not provided
Lot 1 - Civil Engineering NEC4 ECSC V1.1 (1)_Bywell Signed_Redacted
Contains public sector information licensed under the Open Government Licence v3.0.