Design & Implementation of a Track Monitoring Plan
Design & Implementation of a Track Monitoring Plan to facilitate a key temporary solution for the routing of new HV cables which must be connected to buried cables on site at Teesworks. After much exploratory excavation work, it transpires that the excavation required to create a 2m deep Joint Bay, is within the Zone of Influence of the adjacent Network rail tracks. In essence this means that the excavation work required for the project has the ability to compromise the integrity of the railway.
Buyer
TEES VALLEY COMBINED AUTHORITY
Value
£84,981
Published
8 Jan 2024
Closes
15 Dec 2023
Procurement details
Source
Contracts Finder
Region
United Kingdom
Procurement method
Other Direct Award
Category
Services
Contract starts
2 Jan 2024
Contract ends
30 Apr 2024
CPV classifications
71000000
Architectural, construction, engineering and inspection services
Lots
Lot default Design & Implementation of a Track Monitoring Plan
£84,981
Design & Implementation of a Track Monitoring Plan to facilitate a key temporary solution for the routing of new HV cables which must be connected to buried cables on site at Teesworks. After much exploratory excavation work, it transpires that the excavation required to create a 2m deep Joint Bay, is within the Zone of Influence of the adjacent Network rail...
Delivery: North East · United Kingdom, North East, United Kingdom
Documents
Unlock document linkAwarded contract notice on Contracts Finder
8 Jan 2024
Awarded contract notice on Contracts Finder
Award notice · Web page
Contains public sector information licensed under the Open Government Licence v3.0.