Awarded Contractocds-b5fd17-c1b0b573-ba65-4687-9915-81463c87cda7

Analysis into cost of additional underwater noise mitigation during offshore wind farm construction

Increases in offshore wind development are needed to meet the government's target of 40GW by 2030, however construction of these developments has the potential to harm the marine environment. Marine mammals are sensitive to this noise, which has the potential to kill, injure or disturb without appropriate mitigation. A key area of concern is impulsive noise, primarily generated when installing turbine foundations. Developers are already required (as part of the consent process) to implement marine mammal mitigation...

Buyer

Business Energy and Industrial Strategy

Value

£30,000

Published

24 Feb 2022

Closes

24 Jan 2022

Procurement details

Source

Contracts Finder

Region

United Kingdom

Procurement method

Open

Category

Services

Contract starts

9 Feb 2022

Contract ends

31 Mar 2022

CPV classifications

71313000

Environmental engineering consultancy services

Lots

Lot default Analysis into cost of additional underwater noise mitigation during offshore wind farm construction

£30,000

Increases in offshore wind development are needed to meet the government's target of 40GW by 2030, however construction of these developments has the potential to harm the marine environment. Marine mammals are sensitive to this noise, which has the potential to kill, injure or disturb without appropriate mitigation. A key area of concern is impulsive noise,...

Awarded contract notice on Contracts Finder

24 Feb 2022

Awarded contract notice on Contracts Finder

Award notice · Web page

Untitled document

Not provided

Contract signed · PDF

Contains public sector information licensed under the Open Government Licence v3.0.