Works to Install a Sub-Station in Order to Upgrade the Power Supply to EEMac Facility at Newton Aycliffe
The appointed Contractor will be responsible for completing all works required to upgrade the power supply to Unit J732, Durham Way South, Newton Aycliffe. The supply voltage of the connection will be 230/400V +10% or - 6% @ 50Hz AC +1% or - 1%. The contractor will build the substation, Northern Power Grid will then connect the substation to the grid.
Buyer
CENTRE FOR PROCESS INNOVATION LIMITED
Value
£25,000
Published
17 Feb 2017
Closes
6 Mar 2017
Procurement details
Source
Contracts Finder
Region
United Kingdom
Procurement method
Open
Category
Works
Contract starts
Not provided
Contract ends
Not provided
CPV classifications
45232220
Substation construction work
Lots
Lot default Works to Install a Sub-Station in Order to Upgrade the Power Supply to EEMac Facility at Newton Aycliffe
£25,000
The appointed Contractor will be responsible for completing all works required to upgrade the power supply to Unit J732, Durham Way South, Newton Aycliffe. The supply voltage of the connection will be 230/400V +10% or - 6% @ 50Hz AC +1% or - 1%. The contractor will build the substation, Northern Power Grid will then connect the substation to the grid.
Delivery: North East · United Kingdom, North East, United Kingdom
Documents
Unlock document linkOpportunity notice on Contracts Finder
17 Feb 2017
Opportunity notice on Contracts Finder
Tender notice · Web page
Contains public sector information licensed under the Open Government Licence v3.0.