Pipeline Noticeocds-b5fd17-71fec8cc-34ae-4a21-af8b-50d1b4b1db94

Greenwich Power Station - Replacement Gas Turbine

1) Dismantle, removal and disposal of the complete GT/A2 asset including gas turbine, power turbine, alternator and all associated plant/equipment. 2) The design, supply, installation and commissioning of a dual-fuel capable (natural gas and liquid gas oil) open cycle gas turbine package rated to deliver nominal 14MW of power, to fit into the available footprint following the removal of the GT/A2 asset. (approximate space available 22.6m x 7.58m = 171m²).

Buyer

Transport for London

Value

£7,500,000

Published

1 Sept 2021

Closes

1 Sept 2021

Procurement details

Source

Contracts Finder

Region

United Kingdom

Procurement method

Not provided

Category

Goods

Contract starts

Not provided

Contract ends

Not provided

CPV classifications

42112000

Turbine installations

Lots

Lot default Greenwich Power Station - Replacement Gas Turbine

£7,500,000

1) Dismantle, removal and disposal of the complete GT/A2 asset including gas turbine, power turbine, alternator and all associated plant/equipment. 2) The design, supply, installation and commissioning of a dual-fuel capable (natural gas and liquid gas oil) open cycle gas turbine package rated to deliver nominal 14MW of power, to fit into the available footp...

Delivery: England · United Kingdom, England, United Kingdom

Early engagement notice on Contracts Finder

1 Sept 2021

Early engagement notice on Contracts Finder

Market engagement notice · Web page