Open Tenderocds-b5fd17-4a422ec6-adca-11e6-9901-0019b9f3037b

(NU/1210) Supply of an 80kWe RATED Biogas CHP (Combined Heat and Power) Unit

An anaerobic digester (AD) was installed at the Newcastle University site at Cockle Park Farm, Morpeth in 2010. This AD requires a 3-phase supply, and the farm only had 1-phase, so it was run off a 30kW generator. This was insufficient to operate the motors required for solid feedstock (peak demand 72kW). A back-to-back converter rated at 100kW was installed in 2015, enabling the AD to operate with solid feedstock, producing up to 1100 cubic metres of biogas per day. To utilise this biogas effectively, a combined h...

Buyer

NEWCASTLE UNIVERSITY

Value

£130,000

Published

18 Nov 2016

Closes

28 Oct 2016

Procurement details

Source

Contracts Finder

Region

United Kingdom

Procurement method

Not Applicable

Category

Goods

Contract starts

Not provided

Contract ends

Not provided

CPV classifications

31100000

Electric motors, generators and transformers

Lots

Lot default (NU/1210) Supply of an 80kWe RATED Biogas CHP (Combined Heat and Power) Unit

£130,000

An anaerobic digester (AD) was installed at the Newcastle University site at Cockle Park Farm, Morpeth in 2010. This AD requires a 3-phase supply, and the farm only had 1-phase, so it was run off a 30kW generator. This was insufficient to operate the motors required for solid feedstock (peak demand 72kW). A back-to-back converter rated at 100kW was installed...

Delivery: North East · United Kingdom, North East, United Kingdom

Opportunity notice on Contracts Finder

10 Oct 2016

Opportunity notice on Contracts Finder

Tender notice · Web page