Closed – Awaiting Awardocds-b5fd17-3add096a-adc9-11e6-9901-0019b9f3037b

Higher Calderbrook Road Retaining Wall no.2 Reconstruction

The principle purpose of the works is to take down the existing dry stone masonry retaining wall and replace it with a gabion retaining wall faced with masonry as per the design. Reconstruction of the masonry parapet to the specified height (1000mm above finished footway), using the existing and imported material. The employer?s requirements are described in detail in the Specification and the drawings listed in Appendix 0/4 to the Specification. The Contractor shall prepare and complete the specification appendice...

Buyer

Rochdale Borough Council

Value

Not provided

Published

18 Nov 2016

Closes

4 Feb 2016

Procurement details

Source

Contracts Finder

Region

North West

Procurement method

Not provided

Category

Works

Contract starts

Not provided

Contract ends

Not provided

CPV classifications

45223000

Structures construction work

Lots

Lot default Higher Calderbrook Road Retaining Wall no.2 Reconstruction

Value not provided

The principle purpose of the works is to take down the existing dry stone masonry retaining wall and replace it with a gabion retaining wall faced with masonry as per the design. Reconstruction of the masonry parapet to the specified height (1000mm above finished footway), using the existing and imported material. The employer?s requirements are described in...

Delivery: North West · United Kingdom, North West, United Kingdom

Opportunity notice on Contracts Finder

25 Jan 2016

Opportunity notice on Contracts Finder

Tender notice · Web page

Contains public sector information licensed under the Open Government Licence v3.0.